Current Dev Position: YP 3.2 M2

Next Deadline: YP 3.2 M2 build date 2020/7/27

Next Team Meetings:

* Bug Triage meeting Thursday July 30th at 7:30am PDT (
<https://zoom.us/j/454367603> https://zoom.us/j/454367603)
* Monthly Project Meeting Tuesday Aug. 4th at 8am PDT (
<https://zoom.us/j/990892712> https://zoom.us/j/990892712)
* Weekly Engineering Sync Tuesday July 28th at 8am PDT (
<https://zoom.us/j/990892712> https://zoom.us/j/990892712)
* Twitch - See https://www.twitch.tv/theyoctojester

Key Status/Updates:

* This week a build race in perl was tracked down, the other issue of
concern are the qemumips systemd (poky-altcfg) image testing failures (reasons unknown). You can see the list of failures we're continuing to see by searching for the "AB-INT" tag in bugzilla:
<https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT>
https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT

Help with any of these would be much appreciated.

* YP 3.1.2 has been built and is in QA. An issue with toaster and
recent bitake changes may potentially impact the release.
* YP 3.2 M2 will be built this week to follow YP 3.1.2 in QA.
* One way to help the project is to help us with bugs that are
currently unassigned but ideally needed during YP 3.2. See:
<https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_3.2_Unassigned_Enha
ncements.2FBugs>
https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_3.2_Unassigned_Enhan
cements.2FBugs
* Help with any of the recent failed AUH recipe upgrades would also be
appreciated.

YP 3.2 Milestone Dates:

* YP 3.2 M2 build date 2020/7/27
* YP 3.2 M2 Release date 2020/8/7
* YP 3.2 M3 build date 2020/8/31
* YP 3.2 M3 Release date 2020/9/11
* YP 3.2 M4 build date 2020/10/5
* YP 3.2 M4 Release date 2020/10/30

Planned upcoming dot releases:

* YP 3.0.4 build date 2020/8/10
* YP 3.0.4 release date 2020/8/21
* YP 3.1.2 is in QA
* YP 3.1.3 build date 2020/9/14
* YP 3.1.3 release date 2020/9/25

Tracking Metrics:

* WDD 2415 (last week 2450) (
<https://wiki.yoctoproject.org/charts/combo.html>
https://wiki.yoctoproject.org/charts/combo.html)
* Poky Patch Metrics

* Total patches found: 1281 (last week 1275)
* Patches in the Pending State: 498 (39%) [last week 498 (39%)]

The Yocto Project's technical governance is through its Technical Steering Committee, more information is available at:

<https://wiki.yoctoproject.org/wiki/TSC>
https://wiki.yoctoproject.org/wiki/TSC

The Status reports are now stored on the wiki at:
<https://wiki.yoctoproject.org/wiki/Weekly_Status>
https://wiki.yoctoproject.org/wiki/Weekly_Status

[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley

Yocto Project Program Manager

* Cell: (208) 244-4460

* Email: [email protected]
<mailto:[email protected]>